Whittlesea
494 delay minutes
The biggest share (33%) of the delay picked up at Whittlesea in the four weeks to 9 December 2023 came from track faults.
59% of these minutes were knock-on from something that happened elsewhere first. 84% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 161 | 33% | 8% | 6 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 93 | 19% | 16% | 3 a day, more than 3 of the other 4 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 36 | 7% | 7% | 1 a day, the most in 5 years | - |
| External | 23 | 5% | 4% | 1 a day, more than 3 of the other 4 years | - |
| Network management | 121 | 24% | 17% | 4 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 15 | 3% | 16% | 1 a day, the least in 5 years | - |
| Traincrew | 3 | <1% | 11% | 0 a day, the least in 5 years | - |
| Stations | - | - | 3% | 0 a day, the least in 5 years | - |
| Operations | 21 | 4% | 5% | 1 a day, more than 3 of the other 4 years | - |
| Operator, other | 22 | 4% | 7% | 1 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 158 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 25 |
| QJ | Special working for leaf-fall track circuit operation | 24 |
| OU | Delays not Investigated by Network Rail | 22 |
| IC | Track circuit failure (including no fault found) | 20 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 19 |
| J5 | Infrastructure Asset fault reported but proven to be mistaken | 14 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 13 |
| I1 | Overhead line/third rail defect | 12 |
| I5 | Possession over-run from planned work | 11 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 7,976 |
| IC | Track circuit failure (including no fault found) | 2,936 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 1,493 |
| MC | Diesel Loco failure, defect, attention | 905 |
| IA | Signal failure (including no fault found) | 897 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 816 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 815 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 623 |
| JA | TSR speed restrictions for track work outside of the Timetable Planning Rules | 599 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 564 |