6,650 delay minutes

The biggest share (25%) of the delay picked up at Woking in the four weeks to 9 December 2023 came from how the network was run.

57% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track3796%8% 14 a day, more than 2 of the other 4 years7
Signals, points and power1,41521%16% 51 a day, the most in 5 years12
Weather and structures1,27419%7% 46 a day, the most in 5 years24
Autumn4176%7% 15 a day, the most in 5 years-
External39<1%4% 1 a day, more than 1 of the other 4 years1
Network management1,65825%17% 59 a day, the most in 5 years24
The operators' causes
Train faults4066%16% 15 a day, more than 1 of the other 4 years11
Traincrew4447%11% 16 a day, more than 2 of the other 4 years13
Stations991%3% 4 a day, more than 3 of the other 4 years-
Operations891%5% 3 a day, the most in 5 years1
Operator, other4316%7% 15 a day, more than 2 of the other 4 years2

Period by period

Delay minutes a day, period by period. Gridlines every 100 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)1,040
IBPoints failure (including no fault found)863
QBPlanned engineering work - diversion/SLW not timetabled (outside the Timetable Planning Rules)547
ODDelays due to National/Regional/Route Operations directives or Route Control decision or directive376
Q3NZ Pumps T276
TTLeaf fall Neutral274
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.251
ICTrack circuit failure (including no fault found)244
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)234
I5Possession over-run from planned work225
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.11,763
ICTrack circuit failure (including no fault found)9,915
IBPoints failure (including no fault found)9,848
TGDriver9,439
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)7,735
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure6,184
I5Possession over-run from planned work5,811
IRBroken/cracked/twisted/buckled/flawed rail5,581
MDTechnical failures below the solebar5,252
OCSignaller including mis-routing (not ERTM /ETCS related)5,202