Worksop
1,024 delay minutes
The biggest share (37%) of the delay picked up at Worksop in the four weeks to 9 December 2023 came from autumn leaves.
77% of these minutes were knock-on from something that happened elsewhere first. 82% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 128 | 13% | 16% | 5 a day, more than 3 of the other 4 years | 1 |
| Weather and structures | 77 | 8% | 7% | 3 a day, the most in 5 years | 1 |
| Autumn | 374 | 37% | 7% | 13 a day, the most in 5 years | 4 |
| External | 27 | 3% | 4% | 1 a day, more than 2 of the other 4 years | - |
| Network management | 80 | 8% | 17% | 3 a day, more than 1 of the other 4 years | 10 |
| The operators' causes | |||||
| Train faults | 109 | 11% | 16% | 4 a day, more than 1 of the other 4 years | 5 |
| Traincrew | 73 | 7% | 11% | 3 a day, the most in 5 years | 8 |
| Stations | 16 | 2% | 3% | 1 a day, more than 1 of the other 4 years | - |
| Operations | 30 | 3% | 5% | 1 a day, the most in 5 years | - |
| Operator, other | 110 | 11% | 7% | 4 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| QJ | Special working for leaf-fall track circuit operation | 244 |
| Q3 | NZ Pumps T | 98 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 69 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 55 |
| TT | Leaf fall Neutral | 44 |
| OU | Delays not Investigated by Network Rail | 42 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 39 |
| M7 | Door and Door system faults | 35 |
| QI | Cautioning due to railhead leaf contamination | 32 |
| MD | Technical failures below the solebar | 31 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 1,890 |
| TG | Driver | 1,668 |
| M8 | Technical failures above the Solebar | 1,081 |
| Q3 | NZ Pumps T | 1,081 |
| ZU | No Cause Identified After investigation by both Parties | 1,014 |
| M7 | Door and Door system faults | 885 |
| IC | Track circuit failure (including no fault found) | 814 |
| TT | Leaf fall Neutral | 763 |
| Q1 | Takeback Pumps | 727 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 712 |