Leaves on the Line

Whitby

WTB North & East route
CSV JSON

458 delay minutes

The biggest share (32%) of the delay picked up at Whitby in the four weeks to 9 December 2023 came from the operators' own operations.

87% of these minutes were knock-on from something that happened elsewhere first. 90% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track123%8% 0 a day, the least in 5 years-
Signals, points and power347%16% 1 a day, more than 1 of the other 4 years-
Weather and structures6013%7% 2 a day, the most in 5 years-
Autumn4<1%7% 0 a day, more than 1 of the other 4 years-
External--4% 0 a day, the least in 5 years-
Network management4810%17% 2 a day, more than 1 of the other 4 years-
The operators' causes
Train faults419%16% 1 a day, more than 2 of the other 4 years2
Traincrew10723%11% 4 a day, the most in 5 years6
Stations2<1%3% 0 a day, the least in 5 years-
Operations14632%5% 5 a day, the most in 5 years-
Operator, other4<1%7% 0 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TH(Senior) Conductor/Train Manager72
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)66
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail45
TZOther Passenger Train Operating Company causes42
TRTrain Operating Company Directive38
M7Door and Door system faults35
TGDriver35
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles27
OCSignaller including mis-routing (not ERTM /ETCS related)16
IWNon severe weather - snow/ice/frost affecting infrastructure equipment excluding points15
Since 2018
CodeWhat Network Rail loggedMinutes
OTOps Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused)4,274
TGDriver1,530
JSCondition of Track TSR outside the Timetable Planning Rules1,405
JHCritical Rail Temperature speeds, (other than buckled rails)1,326
IBPoints failure (including no fault found)1,132
TZOther Passenger Train Operating Company causes875
RBPassengers joining/alighting826
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)788
MDTechnical failures below the solebar750
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.706