59 delay minutes

The biggest share (24%) of the delay picked up at Watlington in the four weeks to 9 December 2023 came from other operator causes.

80% of these minutes were knock-on from something that happened elsewhere first. 88% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power1322%16%-
Weather and structures--7%-
Autumn712%7%-
External610%4%-
Network management--17%-
The operators' causes
Train faults1322%16%-
Traincrew610%11%-
Stations--3%-
Operations--5%-
Operator, other1424%7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
VHPassenger Communication cord, door egress or emergency train alarm operated10
ICTrack circuit failure (including no fault found)7
M8Technical failures above the Solebar7
QJSpecial working for leaf-fall track circuit operation7
IASignal failure (including no fault found)6
M7Door and Door system faults6
TITraincrew rostering problem6
FWLate start/yard overtime not explained by Operator4
XBVandalism or theft (including the placing of objects on the line)3
XNRoad or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes)3
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,437
I1Overhead line/third rail defect402
TGDriver361
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)360
VHPassenger Communication cord, door egress or emergency train alarm operated269
IASignal failure (including no fault found)222
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles192
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions180
IBPoints failure (including no fault found)172
OCSignaller including mis-routing (not ERTM /ETCS related)162