Weybridge
2,811 delay minutes
The biggest share (21%) of the delay picked up at Weybridge in the four weeks to 9 December 2023 came from signal, points and power faults.
62% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 121 | 4% | 8% | 4 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 580 | 21% | 16% | 21 a day, the most in 5 years | 2 |
| Weather and structures | 77 | 3% | 7% | 3 a day, more than 3 of the other 4 years | - |
| Autumn | 488 | 17% | 7% | 17 a day, the most in 5 years | - |
| External | 13 | <1% | 4% | 0 a day, more than 1 of the other 4 years | - |
| Network management | 522 | 19% | 17% | 19 a day, more than 2 of the other 4 years | 1 |
| The operators' causes | |||||
| Train faults | 202 | 7% | 16% | 7 a day, more than 2 of the other 4 years | 4 |
| Traincrew | 220 | 8% | 11% | 8 a day, more than 3 of the other 4 years | 16 |
| Stations | 96 | 3% | 3% | 3 a day, more than 2 of the other 4 years | - |
| Operations | 9 | <1% | 5% | 0 a day, more than 1 of the other 4 years | 1 |
| Operator, other | 484 | 17% | 7% | 17 a day, more than 2 of the other 4 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 444 |
| TT | Leaf fall Neutral | 444 |
| IB | Points failure (including no fault found) | 323 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 136 |
| TG | Driver | 130 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 114 |
| IJ | AWS/ATP/TPWS/Train stop/On track equipment failure | 88 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 77 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 69 |
| OD | Delays due to National/Regional/Route Operations directives or Route Control decision or directive | 60 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 8,376 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 6,521 |
| IB | Points failure (including no fault found) | 4,558 |
| TG | Driver | 3,789 |
| TT | Leaf fall Neutral | 3,226 |
| IC | Track circuit failure (including no fault found) | 3,160 |
| MD | Technical failures below the solebar | 2,764 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 2,679 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 2,587 |
| Q3 | NZ Pumps T | 2,061 |