Farringdon
560 delay minutes
The biggest share (49%) of the delay picked up at Farringdon in the four weeks to 9 December 2023 came from signal, points and power faults.
48% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 277 | 49% | 16% | 10 a day, the most in 5 years | - |
| Weather and structures | 3 | <1% | 7% | 0 a day, the most in 5 years | - |
| Autumn | 2 | <1% | 7% | 0 a day, the least in 5 years | - |
| External | 10 | 2% | 4% | 0 a day, more than 1 of the other 4 years | - |
| Network management | 99 | 18% | 17% | 4 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 34 | 6% | 16% | 1 a day, the least in 5 years | - |
| Traincrew | 109 | 19% | 11% | 4 a day, more than 3 of the other 4 years | - |
| Stations | 19 | 3% | 3% | 1 a day, more than 1 of the other 4 years | - |
| Operations | - | - | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 8 | 1% | 7% | 0 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| J3 | Axle Counter Failure | 246 |
| TG | Driver | 99 |
| OK | Delay caused by Operating staff oversight, issues or absence (excluding signallers and Control) | 53 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 28 |
| M8 | Technical failures above the Solebar | 17 |
| I1 | Overhead line/third rail defect | 12 |
| TI | Traincrew rostering problem | 10 |
| XB | Vandalism or theft (including the placing of objects on the line) | 10 |
| RX | Station delay due overcrowding due unplanned events or incident (line or station closure) where causal event is not determined | 9 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 9 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 6,024 |
| M8 | Technical failures above the Solebar | 4,156 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,597 |
| IC | Track circuit failure (including no fault found) | 2,370 |
| TI | Traincrew rostering problem | 1,837 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 1,158 |
| I1 | Overhead line/third rail defect | 1,069 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 1,049 |
| IB | Points failure (including no fault found) | 987 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 888 |