Ardrossan Town

ADN Scotland route
CSV JSON

11 delay minutes

Most of the delay picked up at Ardrossan Town in the four weeks to 9 December 2023 came from the operators' own operations.

100% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%2
The operators' causes
Train faults--16%-
Traincrew436%11%-
Stations--3%-
Operations764%5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TATrain-crew/loco/stock/unit diagram issues7
TGDriver4
Since 2018
CodeWhat Network Rail loggedMinutes
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)60
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail49
IASignal failure (including no fault found)42
TGDriver37
MUDepot operating problem30
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)24
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions23
I8Animal Strike or Incursion within the control of Network Rail23
MNBrake and brake systems faults; including wheel flats where no other cause had been identified22
OCSignaller including mis-routing (not ERTM /ETCS related)22