Airdrie
274 delay minutes
The biggest share (41%) of the delay picked up at Airdrie in the four weeks to 9 December 2023 came from other operator causes.
72% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 6 | 2% | 8% | 0 a day, more than 1 of the other 4 years | - |
| Signals, points and power | - | - | 16% | 0 a day, the least in 5 years | 4 |
| Weather and structures | 2 | <1% | 7% | 0 a day, more than 1 of the other 4 years | - |
| Autumn | 26 | 9% | 7% | 1 a day, more than 1 of the other 4 years | - |
| External | 18 | 7% | 4% | 1 a day, more than 3 of the other 4 years | - |
| Network management | 59 | 22% | 17% | 2 a day, more than 3 of the other 4 years | 2 |
| The operators' causes | |||||
| Train faults | 25 | 9% | 16% | 1 a day, the least in 5 years | 5 |
| Traincrew | 17 | 6% | 11% | 1 a day, more than 1 of the other 4 years | - |
| Stations | 6 | 2% | 3% | 0 a day, the most in 5 years | - |
| Operations | 3 | 1% | 5% | 0 a day, more than 1 of the other 4 years | - |
| Operator, other | 112 | 41% | 7% | 4 a day, the most in 5 years | 2 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| VB | Vandalism or theft | 62 |
| OM | Technical failure associated with a Railhead conditioning train | 41 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 24 |
| Q3 | NZ Pumps T | 20 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 19 |
| TG | Driver | 17 |
| XB | Vandalism or theft (including the placing of objects on the line) | 13 |
| M8 | Technical failures above the Solebar | 10 |
| MU | Depot operating problem | 8 |
| I5 | Possession over-run from planned work | 7 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 1,678 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 1,158 |
| M8 | Technical failures above the Solebar | 1,074 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 383 |
| MD | Technical failures below the solebar | 335 |
| IB | Points failure (including no fault found) | 313 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 308 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 304 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 289 |
| M7 | Door and Door system faults | 283 |