37 delay minutes

The biggest share (49%) of the delay picked up at Anderston in the four weeks to 9 December 2023 came from weather and structures.

8% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power1643%16%4
Weather and structures1849%7%1
Autumn24%7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%1
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other24%7%1

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 2 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
X9Points failure caused by severe snow or ice where heaters are fitted and working as designed18
I1Overhead line/third rail defect16
Q3NZ Pumps T2
TTLeaf fall Neutral2
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver218
I2AC/DC trip (including no fault or cause found)208
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)158
IBPoints failure (including no fault found)139
I1Overhead line/third rail defect101
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure78
MPRail / wheel interface, adhesion problems (including ice on the running rail)76
Q3NZ Pumps T66
MNBrake and brake systems faults; including wheel flats where no other cause had been identified62
OUDelays not Investigated by Network Rail60