Ardgay
22 delay minutes
Most of the delay picked up at Ardgay in the four weeks to 9 December 2023 came from track faults.
77% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | 12 | 55% | 8% | - |
| Signals, points and power | - | - | 16% | - |
| Weather and structures | 5 | 23% | 7% | - |
| Autumn | - | - | 7% | - |
| External | - | - | 4% | 1 |
| Network management | - | - | 17% | - |
| The operators' causes | ||||
| Train faults | 5 | 23% | 16% | 1 |
| Traincrew | - | - | 11% | 1 |
| Stations | - | - | 3% | - |
| Operations | - | - | 5% | - |
| Operator, other | - | - | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 12 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 5 |
| MD | Technical failures below the solebar | 5 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 173 |
| MD | Technical failures below the solebar | 118 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 97 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 65 |
| TG | Driver | 63 |
| XO | External trees, building or structures encroaching or falling onto network infrastructure (not weather or vandalism) | 49 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 45 |
| I0 | Telecom equipment legacy radio failures (RETB) | 38 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 36 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 30 |