Ardrossan South Beach
233 delay minutes
The biggest share (30%) of the delay picked up at Ardrossan South Beach in the four weeks to 9 December 2023 came from autumn leaves.
9% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 2 | <1% | 8% | 0 a day, the most in 5 years | - |
| Signals, points and power | 41 | 18% | 16% | 1 a day, the most in 5 years | 4 |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 69 | 30% | 7% | 2 a day, more than 2 of the other 4 years | - |
| External | 3 | 1% | 4% | 0 a day, more than 3 of the other 4 years | - |
| Network management | 11 | 5% | 17% | 0 a day, more than 2 of the other 4 years | 8 |
| The operators' causes | |||||
| Train faults | 14 | 6% | 16% | 1 a day, the most in 5 years | - |
| Traincrew | 13 | 6% | 11% | 0 a day, the most in 5 years | - |
| Stations | 26 | 11% | 3% | 1 a day, the most in 5 years | - |
| Operations | 4 | 2% | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 50 | 21% | 7% | 2 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 46 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 37 |
| OE | Failure to lay Sandite or operate Railhead Conditioning train as programmed | 23 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 15 |
| IA | Signal failure (including no fault found) | 14 |
| TG | Driver | 13 |
| RQ | Un-booked assistance for a person with reduced mobility joining/alighting, | 12 |
| M8 | Technical failures above the Solebar | 11 |
| IC | Track circuit failure (including no fault found) | 10 |
| TT | Leaf fall Neutral | 10 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 3,499 |
| Q3 | NZ Pumps T | 935 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 632 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 625 |
| TG | Driver | 538 |
| TT | Leaf fall Neutral | 454 |
| RQ | Un-booked assistance for a person with reduced mobility joining/alighting, | 398 |
| RB | Passengers joining/alighting | 369 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 334 |
| I8 | Animal Strike or Incursion within the control of Network Rail | 287 |