Aviemore
1,408 delay minutes
Most of the delay picked up at Aviemore in the four weeks to 9 December 2023 came from weather and structures.
75% of these minutes were knock-on from something that happened elsewhere first. 57% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 48 | 3% | 8% | 2 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 181 | 13% | 16% | 6 a day, more than 3 of the other 4 years | - |
| Weather and structures | 768 | 55% | 7% | 27 a day, the most in 5 years | - |
| Autumn | 21 | 1% | 7% | 1 a day, more than 3 of the other 4 years | - |
| External | 9 | <1% | 4% | 0 a day, more than 2 of the other 4 years | - |
| Network management | 119 | 8% | 17% | 4 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 184 | 13% | 16% | 7 a day, the most in 5 years | - |
| Traincrew | 39 | 3% | 11% | 1 a day, more than 3 of the other 4 years | - |
| Stations | 5 | <1% | 3% | 0 a day, the least in 5 years | - |
| Operations | 18 | 1% | 5% | 1 a day, the most in 5 years | - |
| Operator, other | 16 | 1% | 7% | 1 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JK | Flooding not due to exceptional weather | 609 |
| IB | Points failure (including no fault found) | 114 |
| X9 | Points failure caused by severe snow or ice where heaters are fitted and working as designed | 110 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 50 |
| ML | Wagons, coaches and parcel vehicle faults | 47 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 37 |
| M7 | Door and Door system faults | 34 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 33 |
| XT | Severe snow or ice affecting infrastructure which is the responsibility of NR (including implementation of Key Route Strategy) | 30 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 28 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZU | No Cause Identified After investigation by both Parties | 3,367 |
| MD | Technical failures below the solebar | 2,641 |
| TG | Driver | 1,851 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 1,763 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,506 |
| IC | Track circuit failure (including no fault found) | 1,408 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 1,300 |
| X3 | Lightning Strike - damage to protected systems | 1,228 |
| IB | Points failure (including no fault found) | 1,170 |
| JK | Flooding not due to exceptional weather | 1,164 |