Leaves on the Line

Ayr

AYR Scotland route
CSV JSON

12 delay minutes

Most of the delay picked up at Ayr in the four weeks to 9 December 2023 came from signal, points and power faults.

100% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power867%16% 0 a day, more than 1 of the other 4 years-
Weather and structures--7% 0 a day, the least in 5 years-
Autumn433%7% 0 a day, the least in 5 years-
External--4% 0 a day, the least in 5 years-
Network management--17% 0 a day, the least in 5 years3
The operators' causes
Train faults--16% 0 a day, the least in 5 years1
Traincrew--11% 0 a day, the least in 5 years-
Stations--3% 0 a day, the least in 5 years-
Operations--5% 0 a day, the least in 5 years-
Operator, other--7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
ICTrack circuit failure (including no fault found)8
OEFailure to lay Sandite or operate Railhead Conditioning train as programmed4
Since 2018
CodeWhat Network Rail loggedMinutes
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)2,860
TGDriver2,616
ZUNo Cause Identified After investigation by both Parties2,474
IKTelecom equipment failure (including no fault found)2,256
IBPoints failure (including no fault found)1,454
IASignal failure (including no fault found)1,338
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,153
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,091
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)1,069
MDTechnical failures below the solebar1,025