Aberystwyth
2,057 delay minutes
The biggest share (30%) of the delay picked up at Aberystwyth in the four weeks to 9 December 2023 came from how the network was run.
73% of these minutes were knock-on from something that happened elsewhere first. 65% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 33 | 2% | 8% | 1 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 232 | 11% | 16% | 8 a day, more than 3 of the other 4 years | 2 |
| Weather and structures | 22 | 1% | 7% | 1 a day, the least in 5 years | 1 |
| Autumn | 414 | 20% | 7% | 15 a day, the most in 5 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 624 | 30% | 17% | 22 a day, the most in 5 years | - |
| The operators' causes | |||||
| Train faults | 434 | 21% | 16% | 16 a day, the most in 5 years | 6 |
| Traincrew | 198 | 10% | 11% | 7 a day, the most in 5 years | 1 |
| Stations | 10 | <1% | 3% | 0 a day, more than 3 of the other 4 years | - |
| Operations | 65 | 3% | 5% | 2 a day, the most in 5 years | - |
| Operator, other | 25 | 1% | 7% | 1 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 439 |
| QI | Cautioning due to railhead leaf contamination | 219 |
| QH | Adhesion problems due to leaf contamination | 184 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 120 |
| TG | Driver | 120 |
| IC | Track circuit failure (including no fault found) | 101 |
| M7 | Door and Door system faults | 74 |
| M2 | Delay due to ATO / ETCS equipment | 67 |
| TH | (Senior) Conductor/Train Manager | 63 |
| TZ | Other Passenger Train Operating Company causes | 55 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| M0 | Confirmed train cab based safety system fault (including GSMR) | 2,771 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 2,738 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 2,696 |
| MD | Technical failures below the solebar | 2,637 |
| M8 | Technical failures above the Solebar | 2,405 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 2,192 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 2,067 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 2,030 |
| TZ | Other Passenger Train Operating Company causes | 1,869 |
| OU | Delays not Investigated by Network Rail | 1,815 |