Leaves on the Line

Aberystwyth

AYW Wales route
CSV JSON

2,057 delay minutes

The biggest share (30%) of the delay picked up at Aberystwyth in the four weeks to 9 December 2023 came from how the network was run.

73% of these minutes were knock-on from something that happened elsewhere first. 65% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track332%8% 1 a day, more than 2 of the other 4 years-
Signals, points and power23211%16% 8 a day, more than 3 of the other 4 years2
Weather and structures221%7% 1 a day, the least in 5 years1
Autumn41420%7% 15 a day, the most in 5 years-
External--4% 0 a day, the least in 5 years-
Network management62430%17% 22 a day, the most in 5 years-
The operators' causes
Train faults43421%16% 16 a day, the most in 5 years6
Traincrew19810%11% 7 a day, the most in 5 years1
Stations10<1%3% 0 a day, more than 3 of the other 4 years-
Operations653%5% 2 a day, the most in 5 years-
Operator, other251%7% 1 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
OTOps Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused)439
QICautioning due to railhead leaf contamination219
QHAdhesion problems due to leaf contamination184
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps120
TGDriver120
ICTrack circuit failure (including no fault found)101
M7Door and Door system faults74
M2Delay due to ATO / ETCS equipment67
TH(Senior) Conductor/Train Manager63
TZOther Passenger Train Operating Company causes55
Since 2018
CodeWhat Network Rail loggedMinutes
M0Confirmed train cab based safety system fault (including GSMR)2,771
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)2,738
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps2,696
MDTechnical failures below the solebar2,637
M8Technical failures above the Solebar2,405
JSCondition of Track TSR outside the Timetable Planning Rules2,192
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure2,067
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles2,030
TZOther Passenger Train Operating Company causes1,869
OUDelays not Investigated by Network Rail1,815