Balham
1,615 delay minutes
The biggest share (45%) of the delay picked up at Balham in the four weeks to 9 December 2023 came from how the network was run.
73% of these minutes were knock-on from something that happened elsewhere first. 94% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 14 | <1% | 8% | 1 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 179 | 11% | 16% | 6 a day, more than 1 of the other 4 years | - |
| Weather and structures | 37 | 2% | 7% | 1 a day, more than 1 of the other 4 years | - |
| Autumn | 5 | <1% | 7% | 0 a day, the least in 5 years | - |
| External | 38 | 2% | 4% | 1 a day, more than 1 of the other 4 years | - |
| Network management | 726 | 45% | 17% | 26 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 220 | 14% | 16% | 8 a day, more than 2 of the other 4 years | 3 |
| Traincrew | 128 | 8% | 11% | 5 a day, the least in 5 years | - |
| Stations | 18 | 1% | 3% | 1 a day, the least in 5 years | - |
| Operations | 63 | 4% | 5% | 2 a day, more than 2 of the other 4 years | 2 |
| Operator, other | 187 | 12% | 7% | 7 a day, more than 1 of the other 4 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 307 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 167 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 135 |
| TG | Driver | 125 |
| OB | Delayed by signaller not applying applicable regulating policy | 95 |
| MD | Technical failures below the solebar | 78 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 67 |
| J3 | Axle Counter Failure | 55 |
| MB | Electic Loco failure, defect, attention | 49 |
| I1 | Overhead line/third rail defect | 38 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 25,743 |
| TG | Driver | 14,919 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 10,071 |
| OB | Delayed by signaller not applying applicable regulating policy | 7,854 |
| IC | Track circuit failure (including no fault found) | 6,902 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 6,659 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 5,061 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 3,992 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 3,883 |
| M8 | Technical failures above the Solebar | 3,402 |