Briton Ferry
77 delay minutes
Most of the delay picked up at Briton Ferry in the four weeks to 9 December 2023 came from faulty trains.
6% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | - | - | 8% | - |
| Signals, points and power | 5 | 6% | 16% | - |
| Weather and structures | - | - | 7% | - |
| Autumn | - | - | 7% | - |
| External | - | - | 4% | - |
| Network management | 2 | 3% | 17% | - |
| The operators' causes | ||||
| Train faults | 63 | 82% | 16% | - |
| Traincrew | 4 | 5% | 11% | - |
| Stations | 3 | 4% | 3% | - |
| Operations | - | - | 5% | - |
| Operator, other | - | - | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 62 |
| IA | Signal failure (including no fault found) | 5 |
| TG | Driver | 4 |
| T2 | Delay at unstaffed station to non-DOO train | 3 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 2 |
| M8 | Technical failures above the Solebar | 1 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| T2 | Delay at unstaffed station to non-DOO train | 201 |
| TG | Driver | 97 |
| MD | Technical failures below the solebar | 92 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 82 |
| OU | Delays not Investigated by Network Rail | 75 |
| TH | (Senior) Conductor/Train Manager | 61 |
| M9 | Reported fleet equipment defect - no fault found | 57 |
| JA | TSR speed restrictions for track work outside of the Timetable Planning Rules | 44 |
| M7 | Door and Door system faults | 41 |
| OV | Fire or evacuation due to fire alarm of Network Rail buildings other than stations not due to vandalism | 32 |