91 delay minutes
The biggest share (34%) of the delay picked up at Brora in the four weeks to 9 December 2023 came from track faults.
32% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | 31 | 34% | 8% | - |
| Signals, points and power | 13 | 14% | 16% | - |
| Weather and structures | 2 | 2% | 7% | - |
| Autumn | - | - | 7% | - |
| External | - | - | 4% | - |
| Network management | 11 | 12% | 17% | - |
| The operators' causes | ||||
| Train faults | 27 | 30% | 16% | - |
| Traincrew | 7 | 8% | 11% | - |
| Stations | - | - | 3% | - |
| Operations | - | - | 5% | - |
| Operator, other | - | - | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 31 |
| MD | Technical failures below the solebar | 22 |
| IC | Track circuit failure (including no fault found) | 7 |
| TG | Driver | 7 |
| IE | Signalling Functional Power Supply Failure | 6 |
| ZU | No Cause Identified After investigation by both Parties | 6 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 5 |
| Q1 | Takeback Pumps | 5 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 2 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 493 |
| IB | Points failure (including no fault found) | 305 |
| ZU | No Cause Identified After investigation by both Parties | 265 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 210 |
| TG | Driver | 144 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 137 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 136 |
| I0 | Telecom equipment legacy radio failures (RETB) | 136 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 119 |
| XO | External trees, building or structures encroaching or falling onto network infrastructure (not weather or vandalism) | 102 |