Leaves on the Line

Bridge of Orchy

BRO Scotland route
CSV JSON

11 delay minutes

Most of the delay picked up at Bridge of Orchy in the four weeks to 9 December 2023 came from weather and structures.

0% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures11100%7%1
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 2 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)11
Since 2018
CodeWhat Network Rail loggedMinutes
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)154
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions71
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure38
I1Overhead line/third rail defect28
RMWaiting connections from other transport modes13
I8Animal Strike or Incursion within the control of Network Rail8
TGDriver5