Leaves on the Line

Burnside (Strathclyde)

BUI Scotland route
CSV JSON

14 delay minutes

The biggest share (50%) of the delay picked up at Burnside (Strathclyde) in the four weeks to 9 December 2023 came from signal, points and power faults.

50% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power750%16%3
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management429%17%3
The operators' causes
Train faults--16%1
Traincrew321%11%2
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IPPoints failure caused by snow or frost where heaters are fitted but found to be not turned on, not operative or defective7
OCSignaller including mis-routing (not ERTM /ETCS related)4
TGDriver3
Since 2018
CodeWhat Network Rail loggedMinutes
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)69
IBPoints failure (including no fault found)47
VBVandalism or theft21
VHPassenger Communication cord, door egress or emergency train alarm operated15
XPBRIDGE HIT14
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure13
TGDriver12
M8Technical failures above the Solebar10
M0Confirmed train cab based safety system fault (including GSMR)10
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure10