Busby
258 delay minutes
The biggest share (24%) of the delay picked up at Busby in the four weeks to 9 December 2023 came from how the network was run.
89% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | - | - | 16% | 0 a day, the least in 5 years | - |
| Weather and structures | 10 | 4% | 7% | 0 a day, more than 3 of the other 4 years | - |
| Autumn | 45 | 17% | 7% | 2 a day, the most in 5 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 61 | 24% | 17% | 2 a day, the most in 5 years | - |
| The operators' causes | |||||
| Train faults | 59 | 23% | 16% | 2 a day, more than 3 of the other 4 years | 1 |
| Traincrew | 7 | 3% | 11% | 0 a day, the least in 5 years | - |
| Stations | 22 | 9% | 3% | 1 a day, more than 1 of the other 4 years | - |
| Operations | 18 | 7% | 5% | 1 a day, more than 3 of the other 4 years | - |
| Operator, other | 37 | 14% | 7% | 1 a day, the most in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| M7 | Door and Door system faults | 30 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 30 |
| Q3 | NZ Pumps T | 30 |
| QM | Train schedule/STP Process including erroneous simplifiers | 23 |
| ZU | No Cause Identified After investigation by both Parties | 19 |
| OS | Late start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident | 17 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 11 |
| QI | Cautioning due to railhead leaf contamination | 10 |
| MB | Electic Loco failure, defect, attention | 9 |
| RC | re-booked assistance for a person with reduced mobility joining/alighting, | 9 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 749 |
| RB | Passengers joining/alighting | 644 |
| TG | Driver | 561 |
| MD | Technical failures below the solebar | 513 |
| M7 | Door and Door system faults | 510 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 494 |
| M8 | Technical failures above the Solebar | 422 |
| IB | Points failure (including no fault found) | 370 |
| J3 | Axle Counter Failure | 361 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 292 |