Berwick-upon-Tweed
328 delay minutes
The biggest share (28%) of the delay picked up at Berwick-upon-Tweed in the four weeks to 9 December 2023 came from weather and structures.
34% of these minutes were knock-on from something that happened elsewhere first. 94% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 13 | 4% | 8% | 0 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 77 | 23% | 16% | 3 a day, more than 3 of the other 4 years | - |
| Weather and structures | 92 | 28% | 7% | 3 a day, more than 2 of the other 4 years | - |
| Autumn | 3 | <1% | 7% | 0 a day, more than 2 of the other 4 years | - |
| External | 9 | 3% | 4% | 0 a day, the most in 5 years | - |
| Network management | 59 | 18% | 17% | 2 a day, the most in 5 years | - |
| The operators' causes | |||||
| Train faults | 36 | 11% | 16% | 1 a day, more than 2 of the other 4 years | - |
| Traincrew | 14 | 4% | 11% | 1 a day, more than 1 of the other 4 years | - |
| Stations | 4 | 1% | 3% | 0 a day, more than 1 of the other 4 years | - |
| Operations | 4 | 1% | 5% | 0 a day, more than 2 of the other 4 years | - |
| Operator, other | 18 | 5% | 7% | 1 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 57 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 47 |
| JK | Flooding not due to exceptional weather | 39 |
| MW | Weather - effect on T&RS equipment | 32 |
| I1 | Overhead line/third rail defect | 20 |
| OU | Delays not Investigated by Network Rail | 17 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 16 |
| Q1 | Takeback Pumps | 14 |
| FW | Late start/yard overtime not explained by Operator | 12 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 11 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 1,981 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 1,433 |
| I1 | Overhead line/third rail defect | 1,152 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 1,070 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 783 |
| I8 | Animal Strike or Incursion within the control of Network Rail | 704 |
| TG | Driver | 598 |
| X8 | Animal Strike or incursion not within the control of Network Rail | 583 |
| IA | Signal failure (including no fault found) | 578 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 513 |