Leaves on the Line

Cardenden

CDD Scotland route
CSV JSON

26 delay minutes

The biggest share (31%) of the delay picked up at Cardenden in the four weeks to 9 December 2023 came from traincrew problems.

46% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power312%16%-
Weather and structures--7%-
Autumn517%7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew831%11%-
Stations--3%-
Operations623%5%-
Operator, other517%7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 2 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver8
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)6
MPRail / wheel interface, adhesion problems (including ice on the running rail)5
Q3NZ Pumps T5
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure3
Since 2018
CodeWhat Network Rail loggedMinutes
ICTrack circuit failure (including no fault found)273
MDTechnical failures below the solebar248
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)194
TGDriver180
M7Door and Door system faults163
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure137
XRCable vandalism or theft124
IESignalling Functional Power Supply Failure92
Q3NZ Pumps T92
MPRail / wheel interface, adhesion problems (including ice on the running rail)91