Corkerhill

CKH Scotland route
CSV JSON

0 delay minutes

No delay was picked up at Corkerhill in the four weeks to 9 December 2023.

100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%2
Weather and structures--7%1
Autumn--7%-
External--4%1
Network management--17%-
The operators' causes
Train faults--16%1
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%1

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Nothing logged.
Since 2018
CodeWhat Network Rail loggedMinutes
ICTrack circuit failure (including no fault found)47
IBPoints failure (including no fault found)19
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)19
X8Animal Strike or incursion not within the control of Network Rail18
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure13
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)12
I9Fires starting on Network Rail Infrastructure11
TZOther Passenger Train Operating Company causes10
I6Delays as a result of line blocks / track patrols (including late handback)9
JPFailure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards8