Leaves on the Line

Crianlarich

CNR Scotland route
CSV JSON

2,152 delay minutes

The biggest share (32%) of the delay picked up at Crianlarich in the four weeks to 9 December 2023 came from weather and structures.

63% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track924%8% 3 a day, more than 3 of the other 4 years-
Signals, points and power23211%16% 8 a day, the most in 5 years-
Weather and structures69532%7% 25 a day, the most in 5 years1
Autumn774%7% 3 a day, more than 2 of the other 4 years-
External502%4% 2 a day, the most in 5 years-
Network management50824%17% 18 a day, the most in 5 years4
The operators' causes
Train faults30314%16% 11 a day, more than 3 of the other 4 years-
Traincrew944%11% 3 a day, the most in 5 years-
Stations3<1%3% 0 a day, more than 1 of the other 4 years-
Operations3<1%5% 0 a day, more than 2 of the other 4 years-
Operator, other964%7% 3 a day, more than 3 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions427
JPFailure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards258
IBPoints failure (including no fault found)176
MNBrake and brake systems faults; including wheel flats where no other cause had been identified138
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)135
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)120
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure98
JBReactionary Delay to 'P' coded TSRs69
Q1Takeback Pumps66
MDTechnical failures below the solebar63
Since 2018
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions16,759
TGDriver4,726
MDTechnical failures below the solebar4,658
M8Technical failures above the Solebar4,256
ZUNo Cause Identified After investigation by both Parties3,583
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)3,012
IBPoints failure (including no fault found)2,992
MNBrake and brake systems faults; including wheel flats where no other cause had been identified1,865
I0Telecom equipment legacy radio failures (RETB)1,715
M0Confirmed train cab based safety system fault (including GSMR)1,706