Carstairs
646 delay minutes
Most of the delay picked up at Carstairs in the four weeks to 9 December 2023 came from faulty trains.
77% of these minutes were knock-on from something that happened elsewhere first. 75% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 76 | 12% | 16% | 3 a day, more than 2 of the other 4 years | - |
| Weather and structures | 6 | <1% | 7% | 0 a day, more than 1 of the other 4 years | - |
| Autumn | 4 | <1% | 7% | 0 a day, more than 1 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 32 | 5% | 17% | 1 a day, more than 2 of the other 4 years | 46 |
| The operators' causes | |||||
| Train faults | 511 | 79% | 16% | 18 a day, the most in 5 years | 3 |
| Traincrew | 3 | <1% | 11% | 0 a day, the least in 5 years | - |
| Stations | - | - | 3% | 0 a day, the least in 5 years | - |
| Operations | 7 | 1% | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 8 | 1% | 7% | 0 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MB | Electic Loco failure, defect, attention | 199 |
| ML | Wagons, coaches and parcel vehicle faults | 168 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 140 |
| IB | Points failure (including no fault found) | 54 |
| OD | Delays due to National/Regional/Route Operations directives or Route Control decision or directive | 32 |
| IC | Track circuit failure (including no fault found) | 14 |
| IA | Signal failure (including no fault found) | 5 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 4 |
| RD | Attaching/detaching/shunter/watering | 4 |
| V8 | Train striking or being struck by a bird | 4 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ML | Wagons, coaches and parcel vehicle faults | 2,883 |
| MB | Electic Loco failure, defect, attention | 2,830 |
| RD | Attaching/detaching/shunter/watering | 1,844 |
| TG | Driver | 1,630 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 1,584 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 1,124 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 964 |
| MD | Technical failures below the solebar | 933 |
| IB | Points failure (including no fault found) | 926 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 846 |