Craven Arms
1,098 delay minutes
The biggest share (22%) of the delay picked up at Craven Arms in the four weeks to 9 December 2023 came from signal, points and power faults.
47% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 3 | <1% | 8% | 0 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 240 | 22% | 16% | 9 a day, the most in 5 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 98 | 9% | 7% | 4 a day, the most in 5 years | - |
| External | 86 | 8% | 4% | 3 a day, more than 3 of the other 4 years | - |
| Network management | 132 | 12% | 17% | 5 a day, more than 1 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 210 | 19% | 16% | 8 a day, more than 3 of the other 4 years | 1 |
| Traincrew | 115 | 10% | 11% | 4 a day, the most in 5 years | - |
| Stations | 66 | 6% | 3% | 2 a day, the most in 5 years | - |
| Operations | 67 | 6% | 5% | 2 a day, the most in 5 years | 1 |
| Operator, other | 81 | 7% | 7% | 3 a day, the most in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 89 |
| TG | Driver | 82 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 75 |
| M7 | Door and Door system faults | 74 |
| Q3 | NZ Pumps T | 65 |
| TT | Leaf fall Neutral | 65 |
| T2 | Delay at unstaffed station to non-DOO train | 63 |
| TZ | Other Passenger Train Operating Company causes | 59 |
| XP | BRIDGE HIT | 59 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 38 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 2,458 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 2,353 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 1,626 |
| T2 | Delay at unstaffed station to non-DOO train | 1,455 |
| TG | Driver | 1,437 |
| M8 | Technical failures above the Solebar | 1,361 |
| OU | Delays not Investigated by Network Rail | 1,034 |
| TH | (Senior) Conductor/Train Manager | 930 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 818 |
| XN | Road or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes) | 783 |