417 delay minutes

The biggest share (24%) of the delay picked up at Cumbernauld in the four weeks to 9 December 2023 came from other operator causes.

92% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track133%8% 0 a day, more than 2 of the other 4 years-
Signals, points and power287%16% 1 a day, more than 2 of the other 4 years13
Weather and structures102%7% 0 a day, more than 1 of the other 4 years5
Autumn8621%7% 3 a day, the most in 5 years-
External4110%4% 1 a day, the most in 5 years2
Network management348%17% 1 a day, more than 1 of the other 4 years9
The operators' causes
Train faults328%16% 1 a day, more than 1 of the other 4 years3
Traincrew4310%11% 2 a day, more than 3 of the other 4 years2
Stations123%3% 0 a day, the most in 5 years-
Operations174%5% 1 a day, more than 1 of the other 4 years1
Operator, other10124%7% 4 a day, the most in 5 years3

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Q3NZ Pumps T79
MPRail / wheel interface, adhesion problems (including ice on the running rail)69
TGDriver43
XMExternal utility incident including gas, water mains, overhead power lines39
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)14
RQUn-booked assistance for a person with reduced mobility joining/alighting,12
M1Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC)11
TTLeaf fall Neutral11
IBPoints failure (including no fault found)10
JBReactionary Delay to 'P' coded TSRs10
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver2,317
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)1,916
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions1,231
Q3NZ Pumps T643
OCSignaller including mis-routing (not ERTM /ETCS related)568
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)517
MPRail / wheel interface, adhesion problems (including ice on the running rail)509
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure470
M8Technical failures above the Solebar438
OUDelays not Investigated by Network Rail376