Cwmbran
385 delay minutes
The biggest share (37%) of the delay picked up at Cwmbran in the four weeks to 9 December 2023 came from signal, points and power faults.
31% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 141 | 37% | 16% | 5 a day, the most in 5 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | - | - | 7% | 0 a day, the least in 5 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 49 | 13% | 17% | 2 a day, more than 1 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 60 | 16% | 16% | 2 a day, more than 3 of the other 4 years | - |
| Traincrew | 59 | 15% | 11% | 2 a day, more than 3 of the other 4 years | - |
| Stations | 50 | 13% | 3% | 2 a day, the most in 5 years | - |
| Operations | - | - | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 26 | 7% | 7% | 1 a day, the most in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| II | Signalling lineside cable fault | 99 |
| T2 | Delay at unstaffed station to non-DOO train | 46 |
| TG | Driver | 31 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 30 |
| IB | Points failure (including no fault found) | 24 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 19 |
| ML | Wagons, coaches and parcel vehicle faults | 18 |
| AC | Waiting Train preparation or completion of TOPS list/RT3973 | 15 |
| TW | Driver adhering to company professional driving standards or policy | 13 |
| TH | (Senior) Conductor/Train Manager | 12 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 946 |
| MD | Technical failures below the solebar | 895 |
| JA | TSR speed restrictions for track work outside of the Timetable Planning Rules | 816 |
| T2 | Delay at unstaffed station to non-DOO train | 739 |
| J3 | Axle Counter Failure | 728 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 719 |
| M8 | Technical failures above the Solebar | 622 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 579 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 562 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 492 |