Dalmally
50 delay minutes
Most of the delay picked up at Dalmally in the four weeks to 9 December 2023 came from how the network was run.
74% of these minutes were knock-on from something that happened elsewhere first. 86% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | - | - | 8% | - |
| Signals, points and power | 7 | 14% | 16% | - |
| Weather and structures | 13 | 26% | 7% | - |
| Autumn | - | - | 7% | - |
| External | - | - | 4% | - |
| Network management | 30 | 60% | 17% | 1 |
| The operators' causes | ||||
| Train faults | - | - | 16% | - |
| Traincrew | - | - | 11% | - |
| Stations | - | - | 3% | - |
| Operations | - | - | 5% | - |
| Operator, other | - | - | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 30 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 13 |
| IA | Signal failure (including no fault found) | 7 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 701 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 71 |
| MD | Technical failures below the solebar | 58 |
| M8 | Technical failures above the Solebar | 42 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 39 |
| TG | Driver | 34 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 31 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 29 |
| IH | Power Supply And Distribution System Failure | 29 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 28 |