Leaves on the Line

Dundee

DEE Scotland route
CSV JSON

2,474 delay minutes

The biggest share (18%) of the delay picked up at Dundee in the four weeks to 9 December 2023 came from signal, points and power faults.

54% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track1195%8% 4 a day, more than 3 of the other 4 years8
Signals, points and power43518%16% 16 a day, the most in 5 years3
Weather and structures43017%7% 15 a day, more than 2 of the other 4 years9
Autumn1817%7% 6 a day, more than 2 of the other 4 years-
External1857%4% 7 a day, the most in 5 years1
Network management43518%17% 16 a day, more than 2 of the other 4 years35
The operators' causes
Train faults25010%16% 9 a day, more than 2 of the other 4 years17
Traincrew1586%11% 6 a day, more than 2 of the other 4 years15
Stations572%3% 2 a day, more than 1 of the other 4 years-
Operations663%5% 2 a day, more than 2 of the other 4 years-
Operator, other1606%7% 6 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
ZUNo Cause Identified After investigation by both Parties300
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions270
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure146
ICTrack circuit failure (including no fault found)139
Q3NZ Pumps T130
TGDriver127
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure111
MPRail / wheel interface, adhesion problems (including ice on the running rail)105
IASignal failure (including no fault found)100
XPBRIDGE HIT99
Since 2018
CodeWhat Network Rail loggedMinutes
ZUNo Cause Identified After investigation by both Parties16,854
TGDriver6,783
MDTechnical failures below the solebar5,467
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions4,911
M8Technical failures above the Solebar4,098
ICTrack circuit failure (including no fault found)3,548
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,611
IBPoints failure (including no fault found)2,579
IASignal failure (including no fault found)2,552
Q3NZ Pumps T2,427