0 delay minutes

No delay was picked up at Dunfermline Queen Margaret in the four weeks to 9 December 2023.

100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%1
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Nothing logged.
Since 2018
CodeWhat Network Rail loggedMinutes
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)24
TGDriver19
IBPoints failure (including no fault found)9
J3Axle Counter Failure9
IASignal failure (including no fault found)8
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure7
MPRail / wheel interface, adhesion problems (including ice on the running rail)4
Q3NZ Pumps T4
ICTrack circuit failure (including no fault found)3
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)1