Leaves on the Line

Dumfries

DMF Scotland route
CSV JSON

400 delay minutes

The biggest share (27%) of the delay picked up at Dumfries in the four weeks to 9 December 2023 came from how the network was run.

25% of these minutes were knock-on from something that happened elsewhere first. 79% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power3910%16% 1 a day, more than 2 of the other 4 years-
Weather and structures8822%7% 3 a day, more than 3 of the other 4 years3
Autumn143%7% 0 a day, more than 2 of the other 4 years-
External72%4% 0 a day, more than 1 of the other 4 years-
Network management10827%17% 4 a day, more than 3 of the other 4 years38
The operators' causes
Train faults5313%16% 2 a day, more than 1 of the other 4 years8
Traincrew5413%11% 2 a day, the most in 5 years1
Stations103%3% 0 a day, more than 3 of the other 4 years-
Operations--5% 0 a day, the least in 5 years-
Operator, other297%7% 1 a day, more than 3 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
JFOff track asset defects or issues on the NR network (not due to vandalism or weather or part of station infrastructure)68
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions60
TGDriver47
ZUNo Cause Identified After investigation by both Parties31
IASignal failure (including no fault found)26
JKFlooding not due to exceptional weather19
M8Technical failures above the Solebar18
MDTechnical failures below the solebar17
VWSevere weather affecting passenger Fleet equipment including follwogin company standards/policies or Rule book instructions14
M1Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC)12
Since 2018
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions3,077
ZUNo Cause Identified After investigation by both Parties1,225
IBPoints failure (including no fault found)1,146
TGDriver981
MDTechnical failures below the solebar942
IASignal failure (including no fault found)604
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)556
M8Technical failures above the Solebar549
OLSignal Box not open during booked hours470
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure423