Leaves on the Line

Dalmuir

DMR Scotland route
CSV JSON

1,912 delay minutes

The biggest share (21%) of the delay picked up at Dalmuir in the four weeks to 9 December 2023 came from other operator causes.

73% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track915%8% 3 a day, more than 2 of the other 4 years-
Signals, points and power27114%16% 10 a day, more than 3 of the other 4 years26
Weather and structures824%7% 3 a day, more than 3 of the other 4 years16
Autumn30916%7% 11 a day, more than 2 of the other 4 years-
External603%4% 2 a day, more than 2 of the other 4 years3
Network management18810%17% 7 a day, the least in 5 years8
The operators' causes
Train faults26214%16% 9 a day, more than 3 of the other 4 years10
Traincrew1719%11% 6 a day, more than 3 of the other 4 years4
Stations16<1%3% 1 a day, the least in 5 years-
Operations643%5% 2 a day, more than 2 of the other 4 years3
Operator, other39921%7% 14 a day, the most in 5 years9

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Q3NZ Pumps T250
MPRail / wheel interface, adhesion problems (including ice on the running rail)206
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure189
TGDriver164
MNBrake and brake systems faults; including wheel flats where no other cause had been identified110
VWSevere weather affecting passenger Fleet equipment including follwogin company standards/policies or Rule book instructions105
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)80
M8Technical failures above the Solebar80
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.58
TTLeaf fall Neutral48
Since 2018
CodeWhat Network Rail loggedMinutes
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)7,516
TGDriver7,461
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)6,858
M8Technical failures above the Solebar4,573
Q3NZ Pumps T3,105
MPRail / wheel interface, adhesion problems (including ice on the running rail)3,068
IBPoints failure (including no fault found)2,726
MDTechnical failures below the solebar2,217
MNBrake and brake systems faults; including wheel flats where no other cause had been identified2,124
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,098