Leaves on the Line

Drem

DRM Scotland route
CSV JSON

449 delay minutes

The biggest share (26%) of the delay picked up at Drem in the four weeks to 9 December 2023 came from weather and structures.

78% of these minutes were knock-on from something that happened elsewhere first. 92% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track4610%8% 2 a day, more than 3 of the other 4 years-
Signals, points and power7817%16% 3 a day, the least in 5 years-
Weather and structures11526%7% 4 a day, more than 2 of the other 4 years-
Autumn102%7% 0 a day, the least in 5 years-
External123%4% 0 a day, more than 1 of the other 4 years-
Network management7817%17% 3 a day, more than 1 of the other 4 years-
The operators' causes
Train faults235%16% 1 a day, the least in 5 years-
Traincrew276%11% 1 a day, more than 1 of the other 4 years-
Stations235%3% 1 a day, more than 2 of the other 4 years-
Operations307%5% 1 a day, more than 2 of the other 4 years-
Operator, other82%7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)51
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.46
JKFlooding not due to exceptional weather38
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure36
TGDriver27
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions26
I5Possession over-run from planned work24
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)18
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)17
IBPoints failure (including no fault found)14
Since 2018
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions2,998
TGDriver1,479
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,203
I1Overhead line/third rail defect1,044
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail1,030
MDTechnical failures below the solebar1,014
IBPoints failure (including no fault found)911
X8Animal Strike or incursion not within the control of Network Rail908
M8Technical failures above the Solebar885
MNBrake and brake systems faults; including wheel flats where no other cause had been identified845