Dovey Junction
1,182 delay minutes
Most of the delay picked up at Dovey Junction in the four weeks to 9 December 2023 came from how the network was run.
52% of these minutes were knock-on from something that happened elsewhere first. 40% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 18 | 2% | 8% | 1 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 74 | 6% | 16% | 3 a day, more than 1 of the other 4 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 86 | 7% | 7% | 3 a day, more than 3 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 716 | 61% | 17% | 26 a day, the most in 5 years | - |
| The operators' causes | |||||
| Train faults | 111 | 9% | 16% | 4 a day, more than 3 of the other 4 years | - |
| Traincrew | 80 | 7% | 11% | 3 a day, more than 3 of the other 4 years | - |
| Stations | 16 | 1% | 3% | 1 a day, more than 3 of the other 4 years | - |
| Operations | 68 | 6% | 5% | 2 a day, the most in 5 years | - |
| Operator, other | 14 | 1% | 7% | 0 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 585 |
| TZ | Other Passenger Train Operating Company causes | 68 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 61 |
| QH | Adhesion problems due to leaf contamination | 53 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 52 |
| TH | (Senior) Conductor/Train Manager | 46 |
| M2 | Delay due to ATO / ETCS equipment | 33 |
| TG | Driver | 30 |
| IK | Telecom equipment failure (including no fault found) | 24 |
| QI | Cautioning due to railhead leaf contamination | 24 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 2,119 |
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 2,021 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 1,942 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 1,859 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 1,853 |
| MD | Technical failures below the solebar | 1,771 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 1,674 |
| T2 | Delay at unstaffed station to non-DOO train | 1,642 |
| M8 | Technical failures above the Solebar | 1,548 |
| TG | Driver | 1,285 |