740 delay minutes

The biggest share (43%) of the delay picked up at Ebbw Vale Town in the four weeks to 9 December 2023 came from faulty trains.

66% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track3<1%8% 0 a day, the least in 5 years-
Signals, points and power15721%16% 6 a day, more than 2 of the other 4 years11
Weather and structures11415%7% 4 a day, more than 2 of the other 4 years3
Autumn2<1%7% 0 a day, more than 1 of the other 4 years-
External--4% 0 a day, the least in 5 years-
Network management5<1%17% 0 a day, the least in 5 years-
The operators' causes
Train faults32043%16% 11 a day, more than 1 of the other 4 years3
Traincrew385%11% 1 a day, the least in 5 years-
Stations8812%3% 3 a day, more than 1 of the other 4 years-
Operations111%5% 0 a day, the least in 5 years-
Operator, other2<1%7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps210
IKTelecom equipment failure (including no fault found)120
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail114
T2Delay at unstaffed station to non-DOO train88
M0Confirmed train cab based safety system fault (including GSMR)50
TGDriver31
MDTechnical failures below the solebar28
IASignal failure (including no fault found)22
MNBrake and brake systems faults; including wheel flats where no other cause had been identified20
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles15
Since 2018
CodeWhat Network Rail loggedMinutes
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps9,802
T2Delay at unstaffed station to non-DOO train5,139
TH(Senior) Conductor/Train Manager5,024
TGDriver3,409
M8Technical failures above the Solebar2,999
OUDelays not Investigated by Network Rail2,921
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail2,263
MDTechnical failures below the solebar2,209
M7Door and Door system faults1,978
ZYUnivestigated station overtime System Roll-up Only1,781