Ebbw Vale Town
740 delay minutes
The biggest share (43%) of the delay picked up at Ebbw Vale Town in the four weeks to 9 December 2023 came from faulty trains.
66% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 3 | <1% | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 157 | 21% | 16% | 6 a day, more than 2 of the other 4 years | 11 |
| Weather and structures | 114 | 15% | 7% | 4 a day, more than 2 of the other 4 years | 3 |
| Autumn | 2 | <1% | 7% | 0 a day, more than 1 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 5 | <1% | 17% | 0 a day, the least in 5 years | - |
| The operators' causes | |||||
| Train faults | 320 | 43% | 16% | 11 a day, more than 1 of the other 4 years | 3 |
| Traincrew | 38 | 5% | 11% | 1 a day, the least in 5 years | - |
| Stations | 88 | 12% | 3% | 3 a day, more than 1 of the other 4 years | - |
| Operations | 11 | 1% | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 2 | <1% | 7% | 0 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 210 |
| IK | Telecom equipment failure (including no fault found) | 120 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 114 |
| T2 | Delay at unstaffed station to non-DOO train | 88 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 50 |
| TG | Driver | 31 |
| MD | Technical failures below the solebar | 28 |
| IA | Signal failure (including no fault found) | 22 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 20 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 15 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 9,802 |
| T2 | Delay at unstaffed station to non-DOO train | 5,139 |
| TH | (Senior) Conductor/Train Manager | 5,024 |
| TG | Driver | 3,409 |
| M8 | Technical failures above the Solebar | 2,999 |
| OU | Delays not Investigated by Network Rail | 2,921 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 2,263 |
| MD | Technical failures below the solebar | 2,209 |
| M7 | Door and Door system faults | 1,978 |
| ZY | Univestigated station overtime System Roll-up Only | 1,781 |