Eastbourne
1,580 delay minutes
The biggest share (34%) of the delay picked up at Eastbourne in the four weeks to 9 December 2023 came from signal, points and power faults.
79% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 32 | 2% | 8% | 1 a day, more than 1 of the other 4 years | 1 |
| Signals, points and power | 536 | 34% | 16% | 19 a day, the most in 5 years | 1 |
| Weather and structures | 75 | 5% | 7% | 3 a day, more than 3 of the other 4 years | 1 |
| Autumn | 16 | <1% | 7% | 1 a day, more than 3 of the other 4 years | - |
| External | 58 | 4% | 4% | 2 a day, the most in 5 years | 2 |
| Network management | 512 | 32% | 17% | 18 a day, the most in 5 years | 33 |
| The operators' causes | |||||
| Train faults | 118 | 7% | 16% | 4 a day, more than 2 of the other 4 years | 5 |
| Traincrew | 100 | 6% | 11% | 4 a day, the least in 5 years | 8 |
| Stations | 3 | <1% | 3% | 0 a day, more than 1 of the other 4 years | - |
| Operations | 80 | 5% | 5% | 3 a day, more than 3 of the other 4 years | - |
| Operator, other | 51 | 3% | 7% | 2 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IG | Block failure | 229 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 150 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 148 |
| J0 | Telecom equipment radio failure (GSM-R) | 98 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 82 |
| TG | Driver | 80 |
| IK | Telecom equipment failure (including no fault found) | 70 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 66 |
| IB | Points failure (including no fault found) | 63 |
| M8 | Technical failures above the Solebar | 61 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 6,397 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 3,583 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 3,576 |
| TI | Traincrew rostering problem | 2,993 |
| IC | Track circuit failure (including no fault found) | 2,229 |
| M8 | Technical failures above the Solebar | 2,195 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 1,927 |
| TH | (Senior) Conductor/Train Manager | 1,412 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 1,341 |
| J3 | Axle Counter Failure | 1,289 |