Elgin
329 delay minutes
The biggest share (39%) of the delay picked up at Elgin in the four weeks to 9 December 2023 came from weather and structures.
78% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 34 | 10% | 16% | 1 a day, more than 2 of the other 4 years | - |
| Weather and structures | 127 | 39% | 7% | 5 a day, more than 2 of the other 4 years | - |
| Autumn | 6 | 2% | 7% | 0 a day, more than 1 of the other 4 years | - |
| External | 6 | 2% | 4% | 0 a day, more than 1 of the other 4 years | - |
| Network management | 29 | 9% | 17% | 1 a day, more than 1 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 55 | 17% | 16% | 2 a day, more than 2 of the other 4 years | 4 |
| Traincrew | 54 | 16% | 11% | 2 a day, the most in 5 years | - |
| Stations | 3 | <1% | 3% | 0 a day, more than 1 of the other 4 years | - |
| Operations | 10 | 3% | 5% | 0 a day, more than 3 of the other 4 years | - |
| Operator, other | 6 | 2% | 7% | 0 a day, the least in 5 years | 2 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 76 |
| TG | Driver | 46 |
| X9 | Points failure caused by severe snow or ice where heaters are fitted and working as designed | 40 |
| IK | Telecom equipment failure (including no fault found) | 23 |
| ZU | No Cause Identified After investigation by both Parties | 22 |
| ML | Wagons, coaches and parcel vehicle faults | 14 |
| RK | Waiting passenger connections authorised by TOC but outwith TOC/Network Rail connection policy | 10 |
| M7 | Door and Door system faults | 9 |
| MD | Technical failures below the solebar | 9 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 8 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZU | No Cause Identified After investigation by both Parties | 3,260 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 2,166 |
| MD | Technical failures below the solebar | 1,606 |
| TG | Driver | 1,409 |
| M8 | Technical failures above the Solebar | 1,043 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 900 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 857 |
| J3 | Axle Counter Failure | 815 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 721 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 633 |