Leaves on the Line

Elgin

ELG Scotland route
CSV JSON

329 delay minutes

The biggest share (39%) of the delay picked up at Elgin in the four weeks to 9 December 2023 came from weather and structures.

78% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power3410%16% 1 a day, more than 2 of the other 4 years-
Weather and structures12739%7% 5 a day, more than 2 of the other 4 years-
Autumn62%7% 0 a day, more than 1 of the other 4 years-
External62%4% 0 a day, more than 1 of the other 4 years-
Network management299%17% 1 a day, more than 1 of the other 4 years-
The operators' causes
Train faults5517%16% 2 a day, more than 2 of the other 4 years4
Traincrew5416%11% 2 a day, the most in 5 years-
Stations3<1%3% 0 a day, more than 1 of the other 4 years-
Operations103%5% 0 a day, more than 3 of the other 4 years-
Operator, other62%7% 0 a day, the least in 5 years2

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure76
TGDriver46
X9Points failure caused by severe snow or ice where heaters are fitted and working as designed40
IKTelecom equipment failure (including no fault found)23
ZUNo Cause Identified After investigation by both Parties22
MLWagons, coaches and parcel vehicle faults14
RKWaiting passenger connections authorised by TOC but outwith TOC/Network Rail connection policy10
M7Door and Door system faults9
MDTechnical failures below the solebar9
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure8
Since 2018
CodeWhat Network Rail loggedMinutes
ZUNo Cause Identified After investigation by both Parties3,260
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions2,166
MDTechnical failures below the solebar1,606
TGDriver1,409
M8Technical failures above the Solebar1,043
OCSignaller including mis-routing (not ERTM /ETCS related)900
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure857
J3Axle Counter Failure815
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure721
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)633