Leaves on the Line

Ford

FOD Sussex route
CSV JSON

0 delay minutes

No delay was picked up at Ford in the four weeks to 9 December 2023.

100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Nothing logged.
Since 2018
CodeWhat Network Rail loggedMinutes
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure31
IBPoints failure (including no fault found)28
TGDriver23
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.17
IISignalling lineside cable fault15
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail9
OGIce on conductor rail/OHLE5
XRCable vandalism or theft5
M8Technical failures above the Solebar3
Q1Takeback Pumps3