Leaves on the Line

Garrowhill

GAR Scotland route
CSV JSON

0 delay minutes

No delay was picked up at Garrowhill in the four weeks to 9 December 2023.

100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%1
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Nothing logged.
Since 2018
CodeWhat Network Rail loggedMinutes
I2AC/DC trip (including no fault or cause found)73
TGDriver53
XLFire external to but directly affecting the network (incl. line blocks for emergency services attending off network incidents)51
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure30
OGIce on conductor rail/OHLE27
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)22
RBPassengers joining/alighting15
OKDelay caused by Operating staff oversight, issues or absence (excluding signallers and Control)15
IWNon severe weather - snow/ice/frost affecting infrastructure equipment excluding points11
M0Confirmed train cab based safety system fault (including GSMR)11