Garelochhead
817 delay minutes
The biggest share (32%) of the delay picked up at Garelochhead in the four weeks to 9 December 2023 came from weather and structures.
50% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 10 | 1% | 8% | 0 a day, the most in 5 years | - |
| Signals, points and power | 47 | 6% | 16% | 2 a day, more than 2 of the other 4 years | - |
| Weather and structures | 264 | 32% | 7% | 9 a day, the most in 5 years | - |
| Autumn | 25 | 3% | 7% | 1 a day, the most in 5 years | - |
| External | 9 | 1% | 4% | 0 a day, more than 3 of the other 4 years | - |
| Network management | 236 | 29% | 17% | 8 a day, the most in 5 years | - |
| The operators' causes | |||||
| Train faults | 151 | 18% | 16% | 5 a day, the most in 5 years | - |
| Traincrew | 23 | 3% | 11% | 1 a day, more than 3 of the other 4 years | - |
| Stations | 6 | <1% | 3% | 0 a day, the most in 5 years | - |
| Operations | 3 | <1% | 5% | 0 a day, more than 2 of the other 4 years | - |
| Operator, other | 44 | 5% | 7% | 2 a day, the most in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 209 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 177 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 107 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 40 |
| IB | Points failure (including no fault found) | 37 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 26 |
| Q1 | Takeback Pumps | 26 |
| Q3 | NZ Pumps T | 25 |
| TG | Driver | 23 |
| MD | Technical failures below the solebar | 21 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 6,055 |
| MD | Technical failures below the solebar | 1,374 |
| ZU | No Cause Identified After investigation by both Parties | 1,268 |
| IB | Points failure (including no fault found) | 1,227 |
| TG | Driver | 1,138 |
| M8 | Technical failures above the Solebar | 789 |
| I0 | Telecom equipment legacy radio failures (RETB) | 644 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 640 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 536 |
| MC | Diesel Loco failure, defect, attention | 517 |