Glasgow Central Low Level
1,361 delay minutes
The biggest share (18%) of the delay picked up at Glasgow Central Low Level in the four weeks to 9 December 2023 came from faulty trains.
73% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 45 | 3% | 8% | 2 a day, the least in 5 years | - |
| Signals, points and power | 225 | 17% | 16% | 8 a day, more than 3 of the other 4 years | - |
| Weather and structures | 56 | 4% | 7% | 2 a day, more than 2 of the other 4 years | 1 |
| Autumn | 212 | 16% | 7% | 8 a day, more than 3 of the other 4 years | - |
| External | 12 | <1% | 4% | 0 a day, more than 1 of the other 4 years | - |
| Network management | 140 | 10% | 17% | 5 a day, more than 1 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 252 | 18% | 16% | 9 a day, more than 2 of the other 4 years | 2 |
| Traincrew | 113 | 8% | 11% | 4 a day, more than 2 of the other 4 years | 1 |
| Stations | 27 | 2% | 3% | 1 a day, the least in 5 years | - |
| Operations | 73 | 5% | 5% | 3 a day, more than 2 of the other 4 years | - |
| Operator, other | 208 | 15% | 7% | 7 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 178 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 154 |
| TG | Driver | 102 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 79 |
| M8 | Technical failures above the Solebar | 79 |
| I1 | Overhead line/third rail defect | 78 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 61 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 41 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 38 |
| X9 | Points failure caused by severe snow or ice where heaters are fitted and working as designed | 36 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 8,228 |
| TG | Driver | 5,892 |
| M8 | Technical failures above the Solebar | 3,737 |
| IB | Points failure (including no fault found) | 3,072 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 2,514 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 2,433 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,230 |
| Q3 | NZ Pumps T | 2,215 |
| M7 | Door and Door system faults | 2,102 |
| IC | Track circuit failure (including no fault found) | 2,024 |