Leaves on the Line

Glasgow Central Low Level

GCL Scotland route
CSV JSON

1,361 delay minutes

The biggest share (18%) of the delay picked up at Glasgow Central Low Level in the four weeks to 9 December 2023 came from faulty trains.

73% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track453%8% 2 a day, the least in 5 years-
Signals, points and power22517%16% 8 a day, more than 3 of the other 4 years-
Weather and structures564%7% 2 a day, more than 2 of the other 4 years1
Autumn21216%7% 8 a day, more than 3 of the other 4 years-
External12<1%4% 0 a day, more than 1 of the other 4 years-
Network management14010%17% 5 a day, more than 1 of the other 4 years-
The operators' causes
Train faults25218%16% 9 a day, more than 2 of the other 4 years2
Traincrew1138%11% 4 a day, more than 2 of the other 4 years1
Stations272%3% 1 a day, the least in 5 years-
Operations735%5% 3 a day, more than 2 of the other 4 years-
Operator, other20815%7% 7 a day, more than 3 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Q3NZ Pumps T178
MPRail / wheel interface, adhesion problems (including ice on the running rail)154
TGDriver102
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure79
M8Technical failures above the Solebar79
I1Overhead line/third rail defect78
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)61
M1Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC)41
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)38
X9Points failure caused by severe snow or ice where heaters are fitted and working as designed36
Since 2018
CodeWhat Network Rail loggedMinutes
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)8,228
TGDriver5,892
M8Technical failures above the Solebar3,737
IBPoints failure (including no fault found)3,072
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure2,514
MPRail / wheel interface, adhesion problems (including ice on the running rail)2,433
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,230
Q3NZ Pumps T2,215
M7Door and Door system faults2,102
ICTrack circuit failure (including no fault found)2,024