Gordon Hill
440 delay minutes
The biggest share (48%) of the delay picked up at Gordon Hill in the four weeks to 9 December 2023 came from how the network was run.
76% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 6 | 1% | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 18 | 4% | 16% | 1 a day, more than 1 of the other 4 years | - |
| Weather and structures | 12 | 3% | 7% | 0 a day, more than 3 of the other 4 years | - |
| Autumn | 39 | 9% | 7% | 1 a day, more than 2 of the other 4 years | - |
| External | 13 | 3% | 4% | 0 a day, more than 2 of the other 4 years | - |
| Network management | 212 | 48% | 17% | 8 a day, the most in 5 years | 1 |
| The operators' causes | |||||
| Train faults | 25 | 6% | 16% | 1 a day, more than 1 of the other 4 years | 4 |
| Traincrew | 74 | 17% | 11% | 3 a day, more than 2 of the other 4 years | 1 |
| Stations | - | - | 3% | 0 a day, the least in 5 years | - |
| Operations | 8 | 2% | 5% | 0 a day, more than 2 of the other 4 years | - |
| Operator, other | 34 | 8% | 7% | 1 a day, the least in 5 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 57 |
| QB | Planned engineering work - diversion/SLW not timetabled (outside the Timetable Planning Rules) | 48 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 40 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 34 |
| OU | Delays not Investigated by Network Rail | 32 |
| Q3 | NZ Pumps T | 30 |
| TT | Leaf fall Neutral | 27 |
| OD | Delays due to National/Regional/Route Operations directives or Route Control decision or directive | 21 |
| ZU | No Cause Identified After investigation by both Parties | 15 |
| M8 | Technical failures above the Solebar | 12 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 4,167 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 3,739 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,945 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 1,775 |
| I1 | Overhead line/third rail defect | 1,454 |
| MU | Depot operating problem | 1,356 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 1,307 |
| MD | Technical failures below the solebar | 1,250 |
| IA | Signal failure (including no fault found) | 1,105 |
| M8 | Technical failures above the Solebar | 1,093 |