Leaves on the Line

Glasgow Central

GLC Scotland route
CSV JSON

4,885 delay minutes

The biggest share (31%) of the delay picked up at Glasgow Central in the four weeks to 9 December 2023 came from faulty trains.

78% of these minutes were knock-on from something that happened elsewhere first. 86% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track44<1%8% 2 a day, the least in 5 years1
Signals, points and power52611%16% 19 a day, more than 3 of the other 4 years3
Weather and structures54511%7% 19 a day, the most in 5 years24
Autumn1844%7% 7 a day, more than 2 of the other 4 years-
External20<1%4% 1 a day, the least in 5 years8
Network management88818%17% 32 a day, more than 3 of the other 4 years114
The operators' causes
Train faults1,53831%16% 55 a day, the most in 5 years51
Traincrew64813%11% 23 a day, more than 1 of the other 4 years31
Stations912%3% 3 a day, more than 1 of the other 4 years-
Operations1774%5% 6 a day, more than 3 of the other 4 years1
Operator, other2255%7% 8 a day, more than 1 of the other 4 years1

Period by period

Delay minutes a day, period by period. Gridlines every 100 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
M1Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC)584
TGDriver537
M8Technical failures above the Solebar297
MBElectic Loco failure, defect, attention269
X9Points failure caused by severe snow or ice where heaters are fitted and working as designed264
IHPower Supply And Distribution System Failure222
QMTrain schedule/STP Process including erroneous simplifiers169
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)153
Q3NZ Pumps T150
IBPoints failure (including no fault found)141
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver29,253
M8Technical failures above the Solebar13,209
IBPoints failure (including no fault found)12,513
MDTechnical failures below the solebar6,495
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)6,478
MNBrake and brake systems faults; including wheel flats where no other cause had been identified6,146
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure6,102
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions5,582
I1Overhead line/third rail defect5,492
M7Door and Door system faults5,198