Leaves on the Line

Glasgow Queen Street

GLQ Scotland route
CSV JSON

2,007 delay minutes

The biggest share (21%) of the delay picked up at Glasgow Queen Street in the four weeks to 9 December 2023 came from faulty trains.

83% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track432%8% 2 a day, more than 1 of the other 4 years-
Signals, points and power28914%16% 10 a day, more than 3 of the other 4 years7
Weather and structures24712%7% 9 a day, more than 3 of the other 4 years3
Autumn21611%7% 8 a day, the most in 5 years-
External382%4% 1 a day, more than 2 of the other 4 years1
Network management21811%17% 8 a day, more than 1 of the other 4 years72
The operators' causes
Train faults42521%16% 15 a day, more than 2 of the other 4 years15
Traincrew1548%11% 6 a day, more than 2 of the other 4 years8
Stations502%3% 2 a day, more than 1 of the other 4 years-
Operations724%5% 3 a day, more than 2 of the other 4 years-
Operator, other25713%7% 9 a day, the most in 5 years1

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Q3NZ Pumps T195
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions193
MPRail / wheel interface, adhesion problems (including ice on the running rail)172
TGDriver111
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure101
M8Technical failures above the Solebar97
MDTechnical failures below the solebar82
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)63
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)56
MNBrake and brake systems faults; including wheel flats where no other cause had been identified55
Since 2018
CodeWhat Network Rail loggedMinutes
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions9,939
TGDriver9,670
M8Technical failures above the Solebar8,041
MDTechnical failures below the solebar6,179
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)5,669
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure4,111
M7Door and Door system faults3,753
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.3,449
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)3,415
MNBrake and brake systems faults; including wheel flats where no other cause had been identified2,836