Leaves on the Line

Glasgow Queen Street Low Level

GQL Scotland route
CSV JSON

967 delay minutes

The biggest share (18%) of the delay picked up at Glasgow Queen Street Low Level in the four weeks to 9 December 2023 came from other operator causes.

95% of these minutes were knock-on from something that happened elsewhere first. 95% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track10611%8% 4 a day, more than 3 of the other 4 years-
Signals, points and power263%16% 1 a day, the least in 5 years2
Weather and structures192%7% 1 a day, more than 1 of the other 4 years-
Autumn17518%7% 6 a day, more than 3 of the other 4 years-
External152%4% 1 a day, more than 1 of the other 4 years-
Network management12913%17% 5 a day, more than 2 of the other 4 years-
The operators' causes
Train faults14315%16% 5 a day, more than 2 of the other 4 years-
Traincrew11612%11% 4 a day, more than 2 of the other 4 years-
Stations192%3% 1 a day, more than 1 of the other 4 years-
Operations445%5% 2 a day, more than 1 of the other 4 years-
Operator, other17718%7% 6 a day, more than 2 of the other 4 years1

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Q3NZ Pumps T137
MPRail / wheel interface, adhesion problems (including ice on the running rail)114
TGDriver104
JBReactionary Delay to 'P' coded TSRs79
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)59
M8Technical failures above the Solebar59
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)31
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.27
OEFailure to lay Sandite or operate Railhead Conditioning train as programmed25
VHPassenger Communication cord, door egress or emergency train alarm operated25
Since 2018
CodeWhat Network Rail loggedMinutes
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)7,563
TGDriver4,147
M8Technical failures above the Solebar3,073
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,295
MPRail / wheel interface, adhesion problems (including ice on the running rail)2,271
IBPoints failure (including no fault found)2,152
Q3NZ Pumps T2,142
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure1,751
M7Door and Door system faults1,662
OCSignaller including mis-routing (not ERTM /ETCS related)1,630