Garscadden
1,345 delay minutes
The biggest share (22%) of the delay picked up at Garscadden in the four weeks to 9 December 2023 came from other operator causes.
94% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 61 | 5% | 8% | 2 a day, the least in 5 years | - |
| Signals, points and power | 98 | 7% | 16% | 4 a day, the least in 5 years | 8 |
| Weather and structures | 32 | 2% | 7% | 1 a day, more than 1 of the other 4 years | 1 |
| Autumn | 240 | 18% | 7% | 9 a day, the least in 5 years | - |
| External | 31 | 2% | 4% | 1 a day, more than 2 of the other 4 years | - |
| Network management | 140 | 10% | 17% | 5 a day, more than 1 of the other 4 years | 1 |
| The operators' causes | |||||
| Train faults | 206 | 15% | 16% | 7 a day, more than 2 of the other 4 years | 3 |
| Traincrew | 172 | 13% | 11% | 6 a day, more than 2 of the other 4 years | 1 |
| Stations | 16 | 1% | 3% | 1 a day, more than 1 of the other 4 years | - |
| Operations | 51 | 4% | 5% | 2 a day, more than 2 of the other 4 years | 1 |
| Operator, other | 299 | 22% | 7% | 11 a day, more than 2 of the other 4 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 183 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 163 |
| TG | Driver | 162 |
| M8 | Technical failures above the Solebar | 107 |
| VW | Severe weather affecting passenger Fleet equipment including follwogin company standards/policies or Rule book instructions | 81 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 59 |
| OE | Failure to lay Sandite or operate Railhead Conditioning train as programmed | 52 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 45 |
| I1 | Overhead line/third rail defect | 43 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 37 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 9,773 |
| TG | Driver | 7,961 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 4,748 |
| M8 | Technical failures above the Solebar | 4,171 |
| Q3 | NZ Pumps T | 2,943 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 2,934 |
| JB | Reactionary Delay to 'P' coded TSRs | 2,897 |
| M7 | Door and Door system faults | 2,150 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 2,116 |
| IB | Points failure (including no fault found) | 2,018 |