Harlech
59 delay minutes
The biggest share (47%) of the delay picked up at Harlech in the four weeks to 9 December 2023 came from how the network was run.
5% of these minutes were knock-on from something that happened elsewhere first. 53% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | - | - | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 9 | 15% | 16% | 0 a day, more than 2 of the other 4 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | - | - | 7% | 0 a day, the least in 5 years | - |
| External | 11 | 19% | 4% | 0 a day, the most in 5 years | - |
| Network management | 28 | 47% | 17% | 1 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 8 | 14% | 16% | 0 a day, more than 2 of the other 4 years | - |
| Traincrew | - | - | 11% | 0 a day, the least in 5 years | - |
| Stations | - | - | 3% | 0 a day, the least in 5 years | - |
| Operations | - | - | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 3 | 5% | 7% | 0 a day, the most in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 28 |
| XP | BRIDGE HIT | 11 |
| JT | Points failure caused by snow or frost where heaters are not fitted | 9 |
| MT | Confirmed train borne safety system faults (not cab based) | 8 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 3 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OT | Ops Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused) | 3,126 |
| T2 | Delay at unstaffed station to non-DOO train | 1,749 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 971 |
| TZ | Other Passenger Train Operating Company causes | 591 |
| MD | Technical failures below the solebar | 507 |
| M8 | Technical failures above the Solebar | 474 |
| TH | (Senior) Conductor/Train Manager | 408 |
| OU | Delays not Investigated by Network Rail | 398 |
| TG | Driver | 386 |
| J0 | Telecom equipment radio failure (GSM-R) | 380 |