Huntingdon
1,018 delay minutes
The biggest share (28%) of the delay picked up at Huntingdon in the four weeks to 9 December 2023 came from weather and structures.
16% of these minutes were knock-on from something that happened elsewhere first. 89% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 98 | 10% | 8% | 4 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 229 | 22% | 16% | 8 a day, more than 3 of the other 4 years | - |
| Weather and structures | 290 | 28% | 7% | 10 a day, more than 3 of the other 4 years | - |
| Autumn | 30 | 3% | 7% | 1 a day, the most in 5 years | - |
| External | 15 | 1% | 4% | 1 a day, more than 2 of the other 4 years | - |
| Network management | 134 | 13% | 17% | 5 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 165 | 16% | 16% | 6 a day, the most in 5 years | - |
| Traincrew | 24 | 2% | 11% | 1 a day, more than 1 of the other 4 years | - |
| Stations | 19 | 2% | 3% | 1 a day, the most in 5 years | - |
| Operations | 8 | <1% | 5% | 0 a day, more than 3 of the other 4 years | - |
| Operator, other | 6 | <1% | 7% | 0 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 284 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 140 |
| IE | Signalling Functional Power Supply Failure | 130 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 98 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 62 |
| I1 | Overhead line/third rail defect | 35 |
| IA | Signal failure (including no fault found) | 35 |
| QI | Cautioning due to railhead leaf contamination | 28 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 22 |
| OH | ARS / TMS / SARS software problem (excluding scheduling issues and technical failures) | 17 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 3,404 |
| I1 | Overhead line/third rail defect | 3,025 |
| IA | Signal failure (including no fault found) | 2,656 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 2,583 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 2,170 |
| MB | Electic Loco failure, defect, attention | 1,965 |
| II | Signalling lineside cable fault | 1,895 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 1,844 |
| XR | Cable vandalism or theft | 1,735 |
| M1 | Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC) | 1,696 |